Fitout for Suncorp Vero Building, Auckland CBD With Alaska Interiors
Brief
Chillex was appointed to carry out all mechanical services in a retrofit job in the Vero Building, comprising of 5 levels.
Highlights
Unique for its complex staging to accommodate a key feature addition of an internal stairwell linking the 5 floors together, it required major alterations to the existing supply & return systems, VAV units and their associated pipework and controls.
Working in tight confines of the internal staircase
Specially designed swirl and linear diffusers were specifically designed by Holyoake to be installed within the new and existing ceilings.
Work completed successfully within tight time frames with an experienced team on the project combined with a well-coordinated programme and staging plan.